Transportation Projects Moving Along

Highway contractors staying busy with complex bridge, road projects

The U.S. 191 Colorado River Bridge project is the first segmental concrete bridge ever to be constructed in Utah and utilizes a unique form traveler system that was manufactured in China.

By Brad Fullmer

Despite tough economic conditions in the construction industry, contractors working on transportation projects in Utah remain busy, with a host of high-profile projects going on right now.

Below is a glimpse into three key UDOT projects.

U.S. 191 Colorado River Bridge
Moab, Utah

Crews from Draper, Utah-based Wadsworth Brothers Construction have been working on the $38.5-million Colorado River Bridge project over U.S. 191 outside Moab since March. The project is significant in that it is the first segmental concrete bridge ever to be constructed in the Beehive State for the Utah Dept. of Transportation.

Transportation Projects Moving Along
One of two pier tables on the U.S. 191 Colorado River Bridge project just south of Moab.
One of two pier tables on the U.S. 191 Colorado River Bridge project just south of Moab.
A unique form traveler system called Bridge Builder is being utilized on the U.S. 191 Colorado River Bridge project.
A unique form traveler system called Bridge Builder is being utilized on the U.S. 191 Colorado River Bridge project.

Wadsworth Brothers project superintendent Bruce McCabe says there are several challenging aspects of the job, including working with a unique form traveler system called Bridge Builder, which is manufactured in China and soldby NRS-USA of Aventura, Florida.

WBC crews built a temporary 400-ft-long bridge from which to work off of, so as not to disrupt traffic on the existing bridge. Each twin segment bridge over the river is more than 1,000 ft long and is being built in segments using cast-in-place, cantilever post-tensioned segmental construction.

In addition, crews had to build two large piers to support the concrete bridge, one of which is in the middle of the river about 15 ft below the riverbed and gravel. The pier that sits in the middle of the river was constructed by installing a 40-ft-square sheet pile cell designed to withstand high water flows and allow for pier construction below 35 ft of water and streambed pressures. The piers eventually come together, so the challenge is making sure they’re coming toward each other at the right alignment.

In addition, there are several large 7-ft-diameter caissons to support the piers, drilled down up to 155 ft, which project manager Linn Bogart says was extremely difficult for subcontractor Becho Inc. of Salt Lake City.

“It’s the deepest I’ve ever seen, and I’ve been in this business for 30 years,” Bogart says. WBC has 33 crew members on the job, each of whom Bogart says is working more 60-hours-per-week to ensure the project is completed by November 2010.

advertisement

Asked how the construction team is able to figure out such challenges on the fly, McCabe says with a wry chuckle, “Well, I started going to church again. Actually, you have to study and spend some extra time learning the best way to do it. At the end of the day, you can’t just go home, eat some dinner and go to bed – you do have to do a little homework. It’s expected on projects like this.”

Once the southbound bridge is completed, WBC will demolish the existing bridge and replace it with the northbound bridge to accommodate the flow of traffic. As of October 1, WBC crews had completed the pier table deck section for both Piers 2 and 3, and the segmental form travelers were put into position for initial pours. Sixteen ft sections will be poured in one direction, then 16 ft in the other direction to keep the loads balanced. A high-strength concrete mix is being utilized, with 28-day breaks that average around 9,000 psi, according to McCabe. The Bridge Builder traveler form system is designed to have at a 180-ton capacity, according to NRS-USA regional director Jiri Pol.

I-15 EXPRESSLink / Beck Street Expansion
North Salt Lake, Utah

The scope of the Beck Street expansion project is to reconstruct and widen I-15 from 500 North in Salt Lake City to the I-215 overpass in Davis County (over 4 miles in length) to accommodate four lanes, including one express lane in each direction and to provide enough shoulder width for a future fifth lane.

A unique form traveler system called Bridge Builder is being utilized on the U.S. 191 Colorado River Bridge project.
The EXPRESSLink project in North Salt Lake will move this bridge into place via SPMTs.

The project is being constructed by Kiewit-Clyde, a joint-venture between Omaha-based Peter Kiewit & Sons and W.W. Clyde & Co of Springville, Utah.

Crews will replace bridges at Beck Street/I-15 overpass and southbound U.S. 89 overpass and demolish two bridges to be replaced by a new bridge at 1100 North. The U.S. 89 bridge is being built via Accelerated Bridge Construction methods and will be moved into place via Self-Propelled Modular Transports (SPMTs). The other bridges will be built via more traditional cast-in-place methods using drilled shafts and deep soil mixing.

The $115.4-million project started in October 2008 and is slated for completion by October 2010.

Pioneer Crossing; Lehi / I-15 American Fork Interchange
Utah County

The Pioneer Crossing project, which is also being constructed by a Kiewit-Clyde joint venture, begins at American Fork Main Street, crosses over I-15, and continues west to Redwood Road. This $172.1-million job began last November and won’t conclude until October 2010.

A unique form traveler system called Bridge Builder is being utilized on the U.S. 191 Colorado River Bridge project.
Nighttime view of Pioneer Crossing highway project.

The project encompasses six miles of new highway, three bridges, and 21,652 lf of 60 in 200 psi waterline running alongside the alignment. One unique aspect of Pioneer Crossing is the inclusion of the second Diverging Diamond Interchange ever built in the United States. This bridge, with 194-ft concrete girders, will be built using Accelerated Bridge Construction methods. The bridges are being constructed adjacent to I-15 and when finished, will be moved into place using SPMTs.

Mike Seare of Kiewit says both projects remain on schedule, despite both being built in areas with heavy traffic volumes.

“It’s definitely challenging working during times of high traffic,” says Seare. “Our crews are constantly emphasizing safety and being aware of what’s going on around them. These are very complex projects we’re building.”

 

 